[M-AG34] [EJ] 福島原発事故により放出された放射性核種の環境動態

2017年5月25日(木) 13:45 〜 15:15 コンベンションホールA (国際会議場 2F)

コンビーナ:北 和之(茨城大学理学部)、恩田 裕一(筑波大学アイソトープ環境動態研究センター)、五十嵐 康人(気象研究所 環境・応用気象研究部)、山田 正俊(弘前大学被ばく医療総合研究所)、座長:青山 道夫(福島大学環境放射能研究所)、座長:猪俣 弥生(金沢大学)

14:45 〜 15:00

[MAG34-17] 福島第一原子力発電所事故時に海洋へ直接漏洩した137Cs, 90Sr and 3Hの領域海洋シミュレーション

*津旨 大輔1坪野 考樹1三角 和弘1立田 穣1青山 道夫2広瀬 勝巳3 (1.一般財団法人 電力中央研究所、2.福島大学 環境放射能研究所、3.上智大学 理工学部)

キーワード:福島第一原子力発電所事故、領域海洋モデル、直接漏洩、放射性セシウム、放射性ストロンチウム、トリチウム

A series of accidents at the Fukushima Dai-ichi Nuclear Power Plant (1F NPP) following the earthquake and tsunami of 11 March 2011 resulted in the release of radioactive materials to the ocean by two major pathways, direct release from the accident site and atmospheric deposition. Additional release pathways by river input and runoff from 1F NPP site with precipitation and were also effective for coastal zone in the specific periods before starting direct release on March 26 2011. The activities attributable to the direct release were observed adjacent to the 1F NPP site. The sea side impermeable wall was closed at 26 October 2015. We estimated the direct release rate of 137Cs, 90Sr and 3H for more than four-and-a-half years after the accident by the Regional Ocean Model System (ROMS).
Direct release rate of 137Cs were estimated by comparing simulated results and measured activities adjacent to the 1F NPP site (adjacent to 5,6 discharge and south discharge). Direct release rate of 137Cs was estimated to be 2.2 x 1014 Bq/day and decreased exponentially with time to be 3.9 x109 Bq/day by 26 October 2015. Estimated direct release rate have exponentially decreased with constant rate since 4 November 2011. Apparent half-life of direct release rate was estimated to be 346 days. The estimated total amounts of directly released 137Cs was 3.6±0.7 PBq from 26 March 2011 to 26 October 2015. Simulated 137Cs activities attributable to direct release were in good agreement with observed activities, a result that implies the estimated direct release rate was reasonable. Simulated 137Cs activity affected off coast in the Fukushima prefecture.
90Sr/137Cs activity ratio of stagnant water was 0.05 in the basement of the 1F NPP reactor 2 turbine building on 27 March 2011. Direct release rate of 90Sr was estimated to be 1.1 x 1013 Bq/day from 26 March to 6 April 2011 using the activity ratio in stagnant water because the stagnant water released to the ocean in this period (Tsumune et al., 2012). And the temporal change of direct release rate was estimated by the measured 90Sr activity adjacent to 1F NPP. Directly release rate decreased exponentially to 3.9 x 1010 Bq/day by 30 April 2011. The direct release rate was constant and decreased exponentially from 27 June to 16 December 2013. And the direct release rate was 2.9 x 109 Bq/day by 26 October 2015. The estimated total amounts of directly released 90Sr was 208 ± 42 TBq.
3H/137Cs activity ratio of stagnant water was 8.7 x 10-3 in the basement of the 1F NPP reactor 2 turbine building on 27 March 2011. Directly release rate of 3H was estimated to be 1.9 x 1012 Bq/day from 26 March to 6 April 2011 and decreased exponentially by 16 April 2011. The rate was decreased exponentially with constant rate by 26 October 2015. The direct release rate was estimated to be 7.7 x 109 Bq/day at 26 October 2015. The estimated total amounts of directly released 3H was 131 ± 26 TBq.