2017 Fall Meeting

Presentation information

Oral presentation

III. Fission Energy Engineering » 306-1 Nuclear Safety Engineering, Nuclear Installation Safety, PSA

[2C01-06] PRA 1

Thu. Sep 14, 2017 9:30 AM - 11:05 AM Room C (Open Hall - B1 Block)

Chair:Akio Gofuku (Okayama Univ.)

10:15 AM - 10:30 AM

[2C04] Examination about utilization of multi agent system for probabilistic risk assessment

*Kenichi Kanda1, Kazuma Abe1, Hiromichi Miura1, Tomoaki Yoshida1 (1. Central Research Institute of Electric Power Industry)

Keywords:multi agent, MAS, Probabilistic risk assessment, PRA

We conducted the simulation on the correspondence behaviors at nuclear power plant accident by using the multi agent system (MAS) simulation platform "artisoc" and examined the applicability of MAS to probabilistic risk assessment.