III. Fission Energy Engineering » 305-3 Reactor Design, Construction and Examination of Nuclear Power Station, Aseismatic Design, Nuclear Ship

[3B05-09] BWR PCV Design and AP1000 Test Run

Fri. Sep 15, 2017 10:35 AM - 12:00 PM Room B (B12 - B1 Block)

Chair:Yoshihiro Kojima (TOSHIBA)

10:50 AM - 11:05 AM

[3B06] Applicability evaluation of steel plate reinforced concrete structure for primary containment vessel

(15)Pressure Test of Cylindrical Steel Plate Reinforced Concrete Structure

*Hiroyuki Nouji1, Shintaro Narita1, Masashi Tanabe2, Takashi Okayasu3, Junya Kawada3, Ryoichi Nagayama4 (1. Hitachi-GE Nuclear Energy,Ltd., 2. Toshiba Corporation, 3. Kajima Corporation, 4. The Chugoku Electric Power CO.,INC. )

Keywords:primary containment vessel, cylindrical steel plate concrete structure, pressure tightness, failure mode

In order to evaluate structural integrity of steel plate concrete containment vessel (SCCV) for pressure loading under the accident conditions, the pressure test of a cylindrical steel plate reinforced concrete(SC) specimen and its simulation analyses were conducted. In this report, the outline of the test and the results of the test and analyses are presented.