4:25 PM - 4:40 PM
[1F07] Status of JRR-3 corresponding to new regulatory standards
1 Outline
Keywords:JRR-3, new regulatory standards, BDBA
JRR-3 had been confirmed conformation to new regulations on research and test reactor facilities which came into force on 18th December 2013. The application has been submitted to NRA on 26th September 2014. Finally, installment license of JRR-3 was permitted November in 2018.