Japan Society of Civil Engineers 2019 Annual Meeting

Presentation information

第VI部門

リニューアル (9)

Thu. Sep 5, 2019 12:40 PM - 2:10 PM VI-7 (幸町総合教育棟 第21大講義室)

座長:吉田 善紀(鉄道総合技術研究所)

[VI-1018] Measures for the Tokaido Shinkansen Kuzukawa Bridge built on soft ground

*大橋 翼1 (1. 東海旅客鉄道)

Keywords:Soft ground, Subsidence, Bridge, Bridge girder jack up, Bearing replacement

The Kuzukawa Bridge is installed on a soft ground, and is being maintained and managed as a pending problem structure for the Tokaido Shinkansen, and has been Bridge girder jack up once every 20 years. As the settlement amount has converged as a result of the continuous land settlement measurement, the permanent countermeasure method at night was examined, and 200 mm girder lifting and bearing replacement were completed.

Abstract password authentication.
Password is required to view the abstract. Please enter a password to authenticate.

Password