[CS2-16] Application of Building Information Modeling (BIM) for Escape Shaft during Construction Stage in T207 Thomson-East Coast Line, Singapore

〇Lee Khye Keat Khye Keat1, Hiroaki Tagawa1 (1.Shimizu Corporation)

Keywords:Singapore MRT, BIM, ERSS, Shaft Excavation, Rock

This paper is to present the technical and design challenges at Escape Shaft (ES-2) after additional site investigation (SI) discovered higher rockhead elevation as well as discussing the impact of the application of BIM on cost and time consumption for T207 Project located in Northern part of Singapore.