2019 Fall Meeting

Presentation information

Oral presentation

IV. Nuclear Plant Technologies » 403-1 Risk Assessment Technology, Application of Risk Information

[1O01-07] Advanced PRA Methodology

Wed. Sep 11, 2019 10:00 AM - 11:55 AM Room O (Common Education Bildg. 3F A34)

Chair:Koichi Nakamura(CRIEPI)

11:00 AM - 11:15 AM

[1O05] Development of Integrated Risk Assessment Methodology for External Event

Part3:Bayesian estimation for generating fragility curve of high fidelity structure model

*Yoshifumi Katayama1, Toshiaki Sakai1, Yasuki Ohtori2, Hitoshi Muta2 (1. CRIEPI, 2. Tokyo City Univ.)

Keywords:Fragility curve, Bayesian estimation, Seismic PRA, High fidelity structure, Seismic design

We examined a method that can reduce the number of earthquake response analysis required for fragility curve calculation using Bayesian estimation. As a result of applying this method to the water intake structure of a nuclear power plant, the fragility curve by this method becomes comparable with the method of AESJ’s S-PRA standard.