[VI-588] Construction of cast-in-place pile with rock excavation
Keywords:Location punching pile, Test construction
The test construction was conducted by the all-casing construction method on the basis of the investigation boring performed at the design stage, but the support layer was very hard and drilling became impossible along the way. In order to select a method that can be excavated, a method that can be constructed was selected based on multiple test constructions.