[III-263] Test construction of cast-in-place concrete pile in the Shikotsu pumice-fall deposit layer and result of pile-toe load test

*Naoki Sakakibara1, Takahiro Wachi2, Naoya Fujiwara2, Yuma Marumoto1, Shunsuke Nishimura1, Tatsuo Tsubokura1 (1. OBAYASHI CORPORATION, 2. East Nippon Expressway Company Limited)

Keywords:Cast-ln-place concrete pile, Overall casing method, Shikotsu pumice-fall deposit, Pile-toe load test